9. Borough of Ramsey, Milling and Resurfacing of Commuter Parking Lot, Engineer: In House
    Bid Date:07/03/01

Section entitled Milling, 3" Depth reads:

I. Description
    A. Work Included: Provide labor, materials, equipment and supervision necessary to complete the work of this item, and without limiting the generality thereof includes:

  1. Removal of pavement surface.

  2. It is not intent herein to describe all the items and work required of this item. The Contractor shall assure himself that all of the work to be completed shall be accomplished under this item at no additional cost to the Owner.

  3. Disposal of materials.

Say What?
English 101??


8. new Jersey Sports and Exposition Authority, Meadowlands Sport Complex. Pedestrian Bridge Parking Area
    Bid Date: 04/01/01

Descrimtion of Alternate Item # 4 reads:

4. Topseed and soil

Say What?


7. Montgomery Twp. Mill Pond Soccer Field Renovation. Bid Date: 02/16/01

Addendum #1 reads:
"Please be advised that the Township of Montgomery is still scheduled to receive bids for this project on January 25, 2001 at 2:00 p.m. However, the Township has determined that material modifications to the specifications are necessary. Therefore, if bids are submitted on January 25th, they will be returned unopened to the bidders. The Township expects to re-advertise for this project with revised specifications at a later date. "

Say What?


7. Township of Piscataway, Reconstruction of Centennial Ave., Engineer: In House, Bid Date:02/07/01

Article g-25, Protection of Property reads:

"Earth fill shall be used to regrade any properties disturbed during construction, the contractor, use and quantity of which shall be designated by the Engineer from materials available at the job site."

Say What?


6.. Township of Branchburg NJ, Reconstruction Project in the Vicinity of Round Hill Road
Bid Date: 03/14/2000, Engineer: In House

Specifications, section entitled Engineering Control reads:

The enumeration in the contract documents of particular instances in which the opinion, judgment or direction of the Township Engineer shall control the work, or which work shall be performed to the satisfaction, approval or inspection of the Township Engineer, shall not imply that only matters similar to those enumerated shall be so governed and performed under the control of the Township Engineer.

Say What?  Is this sentence really necessary?


5.Township of Green Brook NJ. Reconstruction of Wickett Ave. 
Bid: 12/17/99. Engineer: Van Cleef Engineering Associates, Belle Mead NJ.

On plans page # 2 the note pertaining to drainage inlet reads:

" Reset Inlet Casting From E to B.

Say What? I guess we also Convert inlets by resetting casting up or down.

 


4. Borough of Mountainside NJ. Resurfacing of Mill Lane Section 2 and Lawrence Avenue. 
    Bid Date: 11/15/1999. Engineer: Michael Disko, Union NJ.

Section GC 5-04 B on Page 5-2 Roadway Excavation Unclassified - Payment reads:

"The quantity of Roadway Excavation Unclassified for which payment will be made will be the total surface course area of the roadway or shoulder actually removed as directed, measured in a horizontal plan in cubic yards."

Say What? How do you measure excavation and horizontal plan in cubic yards?


 

3. The Port Authority of New York and New Jersey. General Sitework Construction at Teterboro Airport.
Bid Date: 10/26/99. Engineer: In House

Section 7A,5 Net Cost on page 35 reads:

"(5)For rental for equipment (excluding non-power hand tools) or construction aids (such as scaffolds, ladders, stairs, ramps, runways, platforms, railings, chutes and other such facilities) whether owned or not owned by the Contractor, or a subcontractor, an amount computed pursuant to the clause herein entitled  "Computation of Rental for Construction Equipment", for equipment actually and necessarily used by the Contractor or a subcontractor, approved by the Authority as required by the clause hereof entitled "Approvals of Subcontractors, Purchases, Rentals and Sales" for the performance of the Work required hereunder."

Say What?!! Can we make this sentence any longer? 


 

2. Borough of Sayreville NJ. 1998 Roadway Paving and Reconstruction, Phase III. Bid Date 10/12/99 Engineer: CME Associates, Parlin NJ

Section 2R - Stone And Bankrun Sand And Gravel reads:

"Payment for items such as underdrain and storm sewer that specifically includes stone or bankrun sand and gravel as a component of that item shall be included for payment in the item that requires same."

Say What ?


 1. Borough of New Providence NJ. Reconstruction of Dogwood Lane. Bid Date 09/24/99

 

 

Proposal's Item # 3A description reads:

"Construction of twelve (12 inch) reinforced concrete pipe in second portion only of Dogwood Lane: (First portion located in second portion)"

SAY WHAT?